|
Reinventing a Corridor
Denver's T-REX project nears completion
after five years
By Mark Shaw
 |
One of the T-REX construction milestones
was the rebuilding of the outdated I-25/I-225 interchange
to include a flyover and grade-separated light rail lines.
Courtesy of CDOT |
Denver commuters are eagerly awaiting
the end of an era this summer-the departure of an unwieldy
dinosaur that has squatted in the heart of their city for
five years.
T-REX, the region's $1.67-billion transportation
monster, is pushing steadily toward a fall completion. Construction
on the combined highway and transit project will be complete
Sept. 1, with light rail service beginning in mid-November.
T-REX-short for Transportation Expansion
Project-includes 17 miles of highway improvements to Interstates
25 and 225 in south Denver, including extra freeway lanes
in all segments of the corridor and rebuilding several troublesome
interchanges and outdated bridges. The project also creates
19 miles of new double-track light rail built in the highway
corridor and paralleling both freeways.
"The multi-modal approach gave us
an opportunity to look beyond our traditional highway-transit
boundaries and solve problems together in a bigger way,"
says Cal Marsella, general manager and chief executive officer
of the Denver Regional Transportation District. "Also,
we probably saved around $300 million doing it as a combined
rail and highway project."
The T-REX southeast corridor light rail
will run along the west side of I-25 from south of downtown
Denver to the city's southern suburbs in Douglas County. A
spur line will stretch northeast along the center median of
I-225 into the eastern suburb of Aurora. The transit system
includes 13 new light-rail stations and improvements to the
existing Broadway station on the north end, the purchase of
34 light-rail vehicles, a new maintenance facility and a communications
control center.
The southeast rail line will connect
to Denver's existing light-rail lines that service downtown
and the southwest suburbs. RTD officials estimate that southeast
corridor trains will immediately service more than 38,000
riders a day, with the option of adding more trains and increasing
frequency to meet RTD's forecast of 51,100 to 59,800 weekday
riders in the southeast corridor by 2025.
 |
Where freeway segments had to be
completely rebuilt, crews from Southeast Corridor Constructors
repaved them with concrete.
Courtesy of CDOT |
Despite a demonstrated need for more
transportation capacity in the corridor, some locals initially
were skeptical of the multi-modal approach. They wanted to
add lanes to the freeways and put off construction of light
rail until later.
"But delaying the light rail would
have made it more like a 15- to 20-year build-out," Marsella
says. "It would not have been done nearly as well, and
at tremendous cost, had we waited and added it later."
"Without a doubt, we saved millions
by doing the highway and light rail together, by having them
physically sharing the same corridor," says T-REX project
director Rick Clarke. "I couldn't possibly speak to all
of the benefits that decision has brought, but just the research
and right-of-way savings alone were tremendous."
Easing Congestion
T-REX construction was done under a design-build, guaranteed-maximum-price
contract of $1.18 billion over a five-year schedule. As of
early summer, the project is on time and within budget, says
Tom Howell, project manager for the contractor, Southeast
Corridor Constructors, a joint venture of Kiewit Construction,
Omaha and Denver; and Parsons Transportation Group Inc., Denver.
"We're going to hit our number and our date," he
says. "In fact, the light-rail system will open about
a month earlier than projected." The T-REX light rail
grand opening is scheduled for Nov. 17.
"I don't know of a project in my 34 years in the business
that's gone better than this one," says Tom Norton, executive
director for the Colorado Dept. of Transportation. "It
will solve a lot of problems for Denver commuters who navigate
the south end of I-25 every day to and from work."
Denver's I-25 southeast corridor is the most congested area
in Colorado, CDOT says. I-25 links Denver's two major employment
centers-downtown and the Denver Tech Center-where more than
200,000 people work. Regional growth will add another 150,000
jobs in DTC and downtown over the next 20 years, says the
Denver Regional Council of Governments, a multi-county oversight
group.
 |
The T-REX team worked with dozens
of municipalities to develop light-rail stations that
enhanced their communities and stimulated interest in
transit-oriented development.
Courtesy of CDOT |
CDOT reports that I-25 carries more than 230,000 vehicles
through the area every day, and the southeast corridor includes
the I-25/I-225 interchange, once identified by the U.S. Dept.
of Transportation as the 14th most congested interchange in
the country. The southeast side of the Denver metro area is
also a booming residential area, with the Census Bureau ranking
Douglas County as one of the fastest growing counties in the
U. S.
All of these factors led transportation planners to decide
that simply adding lanes to the freeways was not likely to
solve the congestion. Using both light rail and expanded highway
capacity seemed to be the best solution, but the multi-modal
nature of the project presented its own complications: How
to incorporate a mass transit component into an already crowded
space? How to build this ambitious project safely and efficiently
while the number of vehicles using the corridor increased
every month? How to make all of the infrastructure corrections
at the same time?
More than a dozen bridges, many built in the 1950s, needed
to be replaced, expanded or repaired. The outdated I-25/I-225
interchange had to be completely rebuilt, and drainage on
I-25, a problem for decades, had to be fixed.
The answers evolved from a number of arenas. First, the T-REX
team established a set of goals to guide its decisions, with
public safety and convenience at the top of the list. "We
realized early on that there was no viable alternative to
I-25 through that corridor," Norton says. "There
were no other arterials big enough to handle that volume of
traffic if we wanted to shut down the freeway during the day.
So the alternative to I-25 had to be I-25."
 |
New Light-Rail Maintenance Facility
The 125,000-sq-ft, state-of-the-art Elati Light Rail Maintenance
Facility is where all of the Regional Transportation District's
light-rail fleet will be cleaned, maintained and inspected,
including the 34 new vehicles being added to the system
through T-REX.
The Elati facility was designed and constructed using
openness, natural light and aesthetic treatments on the
interior and exterior of the building. Built by Denver's
M.A. Mortenson, it includes a train washing station, wheel-truing
lathe area, sanding pump station and several maintenance
bays.
© LaCasse Photography |
That meant keeping at least three through-lanes of the freeway
in both directions open from 5:30 a.m. to 8:30 p.m., with
infrequent highway closures at night for utilities, bridge
work and paving. T-REX planners phased the highway expansion
to keep traffic moving through the corridor during the day,
but that required some design and scheduling flexibility.
"We couldn't have solved all of those problems and stayed
on schedule without using design-build," says Del Walker,
T-REX deputy director. "Overall design was about 35%
complete when we got started, and as it evolved, that allowed
us enough flexibility to move quickly through changes as we
went along."
Other critical elements included a proactive quality management
program and an aggressive public relations strategy and public
involvement process. And the fact that all T-REX team members
were based in a central office helped foster the feeling that
they were T-REX employees, whatever their agency roots.
"We created a brand new organization out of three different
cultures-CDOT, RTD and the consultants," Clarke says.
"We created a T-REX culture."
They carried T-REX business cards and learned to solve problems
as a team. "There were no issues resolved outside of
the T-REX team," Clarke says. "No heavy-handed oversight
from our respective agencies. We intentionally picked people
for T-REX who could handle that approach."
Marsella and Norton and their agencies supported the team
atmosphere. "We insisted upon the structure of a completely
separate entity," CDOT's Norton says. "That wasn't
always easy for me, or for others here at CDOT, to rein ourselves
in and not meddle, but we realized it was the only way for
the T-REX team to function like they needed to."
The team worked with dozens of municipalities and businesses
to develop designs for the light-rail stations that enhanced
their neighborhoods and afforded the best opportunities for
transit-oriented development along the corridor.
"This project generated a tremendous amount of transit-oriented-development
interest at almost every station," RTD's Marsella says.
"It was a real learning experience for some of the communities,
and T-REX was an important part of that learning curve. But
we're not in the development business, so we tried to educate
people on the other side to make that happen. Ultimately,
I think this project will transform Denver, and the model
it creates will help other cities who may want to do the same
thing."
PROJECT TEAM
Project Partners:
Colorado Dept. of Transportation
Regional Transportation District
Federal Transit Administration
Federal Highway Administration
Design-Build Contractor:
Southeast Corridor Constructors, a joint venture between
Kiewit Construction Co. and Parsons Transportation Group
Inc.
Elati Maintenance Facility Contractor:
M.A. Mortenson Co.
Light-Rail Vehicle Supplier:
Siemens Transportation Systems |
PROJECT DETAILS
Scope of Highway Work: 17 miles of highway improvements,
including:
> complete rebuilding of the I-25/I-225 interchange
and eight other interchanges.
> expansion of I-25 to four through-lanes in each direction
from Logan south to I-225.
> expansion of I-25 to five through-lanes in each direction
from I-225 to C-470/E-470.
> expansion of I-225 to three through-lanes in each
direction from I-25 east to Parker Road.
Cost: $795 million
Scope of Light Rail Work: 19 miles of new double-track
light rail system, including:
> west-side alignment along I-25 from Broadway to Lincoln
Avenue.
> median alignment along I-225 from I-25 to Parker
Road.
> 13 new rail stations with parking at 12 of them.
> no at-grade crossings.
> new maintenance facility.
Cost: $879 million |
T-REX FUNDING
> T-REX was funded using no new or increased taxes.
In November 1999, Denver voters approved two bond issues
that partially funded the project and endorsed the addition
of light rail through the southeast corridor.
> Design-build contract with Southeast Corridor Constructors
worth $1.18 billion.
> Light rail costs: $879 million, with $437 million
coming from RTD and local matching funds; $525 million
from an FTA full-funding grant agreement.
> Highway costs: $795 million, from highway users taxes
and matching federal revenue.
> Cost of 34 new light-rail vehicles: $91.8 million.
> Cost of building the Elati Light Rail Maintenance
Facility: $39.5 million. |
|