|
|
Navigating the Minefield: The Legalities
of Terminating Subs
Contractors should use every reasonable
means to avoid a termination, but communication, documentation
and legal advice help avoid trouble later on
|
|
Salvatore N. Fornaciari, Esq.
ATTORNEY AT LAW
Salvatore N. Fornaciari of
Fornaciari & Associates LLC, Southington, Conn.,
handles business and construction disputes, from investigations
to appeals, as well as mediation and arbitration.
Website: www.snflaw.com
|
One of the most difficult decisions a
general contractor faces is whether to terminate a subcontractor.
In a typical scenario, the sub is falling significantly behind
schedule on critical path work. The GC may then be facing
substantial costs in liquidated damages for late completion
if the sub continues. On the other hand, if the GC terminates
the sub, high costs are almost unavoidable: Litigation frequently
follows the termination, and completion subcontractors-like
attorneys-will not be cheap.
When faced with this lose-lose situation,
the GC should first consider alternatives to termination.
If termination is unavoidable, however, the GC must know how
to navigate through the legal minefield.
Alternatives to Termination
The GC should use all reasonable means to avoid termination,
keeping in mind how a judge, jury or arbitrator might later
view these actions. A first step is for the GC and the sub
to communicate effectively with each other.
Typically, real communication between them breaks down and
a letter-writing campaign ensues. The lack of communication
is a breeding ground for disputes. The parties should have
a face-to-face discussion to identify the problem. For example,
perhaps the sub lacks administrative personnel to handle the
notorious paperwork on public projects or maybe it has major
equipment problems.
Once the problem is identified, the GC should consider the
following options to assist the sub:
- Helping with administrative burdens.
- Reducing the scope of work.
- Supplementing work force or equipment.
Contract Terms
As with anything else in life, it pays to be proactive. The
general contractor should be certain it has the proper contract
rights, including the right to complete the work and withhold
payments due to the sub pending completion. If the amount
to finish the work exceeds payments due the sub for its completed
work, the terms should state that the sub is liable for the
difference.
Another important subject is the general contractor's ability
to be paid for all attorneys' fees and costs relating to the
termination. Also, the general contractor should have the
option to mediate and/or arbitrate any dispute.
Furthermore, the GC should ensure that any "Application
for Payment" forms submitted to the owner after the sub's
termination are consistent with its contract rights. For example,
the American Institute of Architects application form states,
in relevant part, that "all amounts have been paid by
the Contractor for Work for which previous Certificate for
Payment were issued and payments received from the Owner...."
Documentation
All projects should be well documented to ensure there is
proper evidence for any potential litigation. Most important,
the general contractor should always document the condition
of the project as it progresses and not wait until termination
is imminent. A series of pictures showing the progress, or
the lack of progress, can be a powerful tool.
Before termination, the GC should take the following actions:
- Write detailed notes about any conversations with the
sub.
- Write detailed letters or notes concerning any opportunities
to cure.
- Attach to those letters any information that might be
relevant, such as sketches indicating a reduced scope of
work.
- Always follow the notice provisions in strict compliance
with the contract.
Mitigation of Damages
In addition to demonstrating that termination was proper,
the general contractor must also show its resulting damages
in any litigation. Damages, however, are limited under the
contract principle of mitigation of damages. This means that
nonbreaching parties cannot simply sit idly by while damages
accumulate. Instead, they must take all reasonable steps to
minimize damages.
Although that principle sounds simple in theory, mitigation
of damages is often a contentious point in termination cases.
The problem is that the cost to complete the remaining work
is typically extremely high when compared to the amount of
work remaining under the original contract. For example, the
general contractor may have terminated the steel sub when
50% of the work was completed on its $500,000 subcontract.
Yet the cheapest completion sub costs $400,000, instead of
$250,000.
Construction industry leaders understand that completion
subs are very costly because of the risks of completing someone
else's work, the limited availability of subs and the general
contractor's diminished bargaining power. Nevertheless, a
lay jury or a judge may have difficulty understanding the
reasons for the high cost of completion.
The contractor should take the following steps to avoid that
danger:
- Take detailed notes about all efforts used to obtain completion
subs.
- Obtain written estimates from available completion subs..
- Take detailed notes about any efforts to negotiate with
all of the available completion subs.
|
Ten Tips to Avoid Trouble:
> Never make a termination judgment when tempers
are flaring.
> Communicate with the sub.
> Consider alternatives to termination.
> Consult with an attorney.
> Contract terms should favor the GC with respect
to completion rights, withholding funds pending completion,
liability for completion, attorneys' fees and mediation/arbitration.
> Ensure that the standard forms submitted after
termination, such as "Application for Payment,"
are consistent with contract rights.
> Always use pictures/video to document progress
of project.
> Document all communications with the sub when
termination is imminent.
> Strictly comply with all notice provisions in
the contract.
> Document all efforts used to obtain a completion
sub.
|
|