|
Traps for the Unwary Contractor: Releases
in Project Documents
Change orders and payment applications
often force contractors to release some rights agreed upon
in the original contract documents
|
|
J. Bradford
McIlvain
ATTORNEY AT LAW
McIlvain
is deputy chair of Dilworth Paxson's Litigation Department
and co-chair of its Construction Group. His practice
focuses on representing owners and contractors in disputes
involving an array of construction projects.
E-mail: jmciIlvain@dilworthlaw.com
|
 |
 |
Natalie
D'Amora
ATTORNEY AT LAW
D'Amora
is a member of Dilworth Paxson's Litigation Department
and its Construction Group. Her practice includes litigation
in state and federal courts relating to contractual,
construction, commercial lending and insurance coverage
disputes.
E-mail: ndamora@dilworthlaw.com
|
Many documents are generated, issued
and signed during the course of a construction project. Some
standard documents, like change orders and payment applications,
may contain provisions that release important contractor rights.
A release may be overlooked by a contractor who views such
provisions as irritating legalese or form language.
However, contractors who ignore such
language do so at the peril of losing important rights, including
the potential to recover for additional work or claims for
compensation for delays, impacts or inefficiencies.
Recognizing Releases
Contractors should be wary of contract provisions that contain
terms like release, waive, surrender, relinquish or abandon.
A release is where one party relinquishes all rights to a
claim or some limited rights, like recovering claims from
delays or extra work. Releases typically arise in two types
of project documents-change orders and payment applications.
Although change orders are a common occurrence, their significance
should not be underestimated because a provision in a change
order can alter or release rights outlined in the original
contract.
As a condition for payment, a contractor may be required
to submit a payment application and, where applicable, a lien
waiver for the payment amount. A payment application may also
include more general release provisions beyond the lien waiver,
such as statements that the release is provided in consideration
of the amounts and sums received by the contractor, and that
the contractor agrees to release all claims arising from the
project.
Legal Effect of Releases
By signing a document that contains a release, contractors
may waive their right to recover on extra work and delay claims.
The scope of a release will generally cover only those claims
expressly identified in the release.
Courts can enforce releases even if a party claims it didn't
intend to release certain rights, which means that contractors
cannot successfully claim they didn't know about the release
or hadn't read it before they signed it. Some courts also
will enforce clearly drafted releases even if the circumstances
indicate that the contractor did not intend to release the
claims.
For example, in one case, a subcontractor sued a general
contractor to recover claims for extra work, delays and inefficiencies.
During the project, the subcontractor executed payment applications
that contained broad releases of the contractor's right to
recover such claims. However, at the same time, the subcontractor
provided oral and written notice to the general contractor
about its extra work, delay and inefficiency claims.
The subcontractor argued that its timely conduct of submitting
delay claims proved it did not intend to release the claims
at issue. The court refused to consider the parties' intentions
and held that the clear language of the release prevailed;
therefore the subcontractor's claims were barred.
Limitations
Releases contain some important legal limitations. They apply
only to claims that arise on or before the date of the release.
Another more limited protection for contractors is that releases
can be narrowly interpreted to prevent overreaching by the
party benefiting from the release, meaning that a court will
not stretch it to cover situations not detailed in the release.
A release is not effective if it was executed and procured
by fraud, duress, accident or mutual mistake. However, those
defenses are generally very difficult to prove, particularly
in disputes between sophisticated businesses.
Protecting Your Rights
The best way to avoid problems with releases is to negotiate
a contract that does not require you to sign a release before
receiving progress payments. In addition, agree on the forms
you will use for change orders and payment applications before
entering into a contract with the owner. Unfortunately, this
is sometimes not possible in bidding situations where the
contract terms are not negotiated, and the contract presents
a "take-it-or-leave-it" situation.
After you enter into the contract, you may still have an
opportunity to negotiate with the owner about the forms for
payment applications and change orders. You can suggest using
the standard change order forms and payment applications,
which do not contain releases, and adequately protect all
parties involved. You can also try to get the owner to include
a statement that explicitly reserves your rights.
As a last resort, if presented with a change order or payment
application that contains a release, you can refuse to sign
it, but you should do that only after consulting with counsel
because the owner may have the contractual right to refuse
payment for work you have performed or for additional work.
Because a contractor signs the release just to get paid is
generally not reason enough to void the release.
On the other hand, an owner who refuses to make undisputed
progress payments solely because you refused to sign the release
may be at risk for violating your state's prompt payment act.
In a recent decision, a court decided that a general contractor
who withheld money to obtain a release had engaged in coercive
negotiation tactics that violated the state's prompt payment
act.
Releases should be entered into only after careful consideration
of your rights. Read your change order and payment application
forms at the beginning of each project so that you can take
all necessary steps to protect your rights.
|
> Negotiate a contract that does not require you
to sign releases to receive progress payments.
> At the outset of a project, agree on the form
of your payment applications and change orders.
> The form you agree on should expressly reserve
the right for both parties to recover for any claims
authorized under the contract.
> The employee empowered to sign change orders and
payment applications should be trained to recognize
questionable releases and encouraged to review the forms
with a legal counsel.
> Document any claims you may have for extra work,
delays and/or inefficiencies as soon as you know about
the claim.
> If you realize during a project that you have
signed releases you did not intend to sign, immediately
consult with counsel to mitigate any damages.
|
|