|
Lone Star CONNECTION
TxDOT's first public-private partnership
paves way for faster delivery of a new Austin tollway
By Eileen Schwartz
 |
| Construction is under way on the
outskirts of Austin on approximately 20 miles of the 49-mile
project to be completed by December 2007. |
Like most states, Texas has its share
of toll road critics. But by using alternative delivery methods,
a much-needed congestion relief project in Central Texas could
be completed 25 years ahead of a traditional bid process.
"In Texas, it's obvious that there's
not enough money around to increase our infrastructure and
still maintain what we've already built," says Tim Weight,
director of turnpike construction with the Texas Dept. of
Transportation's Austin District. "The result may be
that tolls are a user fee, which is really what they are.
If you want to use it, then you pay for it. It makes that
section of road more or less self-supporting."
In its first-ever design-build contract
and the largest single highway project in the state's history,
TxDOT is partnering on a new tollway with a consortium of
firms working as the joint venture of Lone Star Infrastructure.
LSI is comprised of Fluor Corp., Aliso Viejo, Calif.; Balfour
Beatty Construction, Atlanta; and T.J. Lambrecht, Euless,
Texas, all AGC members. Also involved is Omaha's HDR Engineering
Inc. acting as the owner's representative, and more than 20
subcontractors and consultants.
They have teamed up to build the 49-mile,
$1.5-billion State Highway 130, an Austin to San Antonio corridor
designed to relieve congestion by creating a commuter and
NAFTA-traffic alternative to Interstate 35.
 |
| S.H. 130/45 is just one major interchange
within the Central Texas Turnpike Project. The project
includes a number of different delivery methods and an
innovative mix of financing. |
"The challenge associated with S.H.
130 is to build a facility that would improve both safety
and mobility in the I-35/ NAFTA corridor," says Robert
B. Daigh, TxDOT district engineer for the Austin District.
"The Austin/San Antonio section of I-35 is one of the
most congested in the state. We needed to find a more efficient
way to deliver the needed improvements."
The project broke ground in October 2003
on the four-lane divided concrete road that will run parallel
to and east of I-35, extending from just north of the Austin
suburb of Georgetown to U.S. 183 in southeast Travis County.
TxDOT says a second section will be built through Caldwell
and Guadalupe counties, extending the roadway's length to
90 miles.
LSI won the job bidding concrete, even
though its bid was higher than one submitted by Granite Construction
Inc., Watsonville, Calif. Granite proposed using asphalt because
of the region's expansive clays. But LSI's long-term maintenance
estimate of $64.5 million over 15 years won over state officials.
Still, some sections will require soil undercutting and reconditioning
to 72 in. deep.
S.H. 130 is progressing at breakneck
speed. Only 18 months after groundbreaking, construction is
under way on nearly 20 miles of tollway. With a five-year
timetable, construction should be completed no later than
December 2007.
"We have more than half of the right-of-way
in hand," Weight says. "The biggest milestone is
just the fact that we've defined our procedures and processes
to the point where things seem to be going smoothly."
Delivering the Job
S.H. 130 is the largest element of the $3.6- billion Central
Texas Turnpike Project, a 65-mile, mixed-delivery set of toll
roads and interchanges. It's the first road to be developed
under a TxDOT design-build contract known as a Comprehensive
Development Agreement, authorized by the Texas Legislature
in 2001.
CDA is a project delivery method that allows design and construction
to be provided by one entity and performed concurrently. On
S.H. 130, design concepts from other proposers were incorporated
in the project, resulting in a savings of approximately $75
million. The proposers were compensated for their work.
"By partnering with the private sector through a CDA,
we have been able to design, acquire right-of-way, construct
and move utilities quickly and proficiently," Daigh says.
CTTP project delivery includes both traditional and design-build
methods. The project is financed by nearly $700 million in
state highway funds, a U.S. Dept. of Transportation TIFIA
loan and local contributions for right-of-way and bond proceeds.
Texas was the first state to snag a TIFIA loan offered under
the federal Transportation and Infrastructure Finance and
Innovation Act. The $916.75-million loan carries a 5.41% interest
rate but won't be accessed for about five years, when construction
costs begin to come due. In the interim, work is being funded
through short-term bond notes that have an interest rate about
2% lower. TxDOT should save between $60 million and $70 million
in interest by the time it takes possession of the loan.
"The S.H. 130 project as part of the CTTP in the 2002
bond sale provided a fixed-price, fixed-schedule element,"
says Jeff Curren, HDR senior vice president. "That provided
reassurance to the bond market that there are not going to
be a lot of changes associated with these construction costs
for that element of the work."
 |
| Tollway project includes 125 bridges
and eventually may include light rail within its corridor. |
LSI was on board from the beginning, its three firms having
come together several years before submitting their proposal
to TxDOT in February 2002. "When we received the notice
to proceed for right-of-way acquisition and final design and
construction, we had to define the limits of the project so
we knew how much right-of-way to acquire," says Douglas
A. Fuller, LSI project director with Fluor. "While we
were acquiring right-of-way, we were finishing design and
putting together support to start construction."
The design-build nature of the project sets it apart from
the traditional design-bid-build process in other ways. In
addition to concurrent right-of-way acquisition and engineering
being handled by LSI rather than by the state, independent
quality control on both design and construction teams are
part of the organization, providing oversight for the state
while working closely with the rest of the partners.
"Design-build is an allocation of risk for TxDOT,"
Weight says. "The intent is to give the contractor some
latitude to determine his own path forward as he builds the
project. He can move alignment, restack interchanges or buy
more right-of-way rather than building retaining walls, so
he can give us the most economical prices."
Throughout the early stages of the project, teams were assembled
that included a representative from LSI, quality assurance
and the owner to analyze, finalize and refine the design as
well as oversee the design criteria as it was being developed.
The same team spirit carries over to the construction. "The
project embraces partnership on many different levels of the
organization," Fuller says. "A project of this magnitude
and scope requires a good partnering relationship between
the owner and the design-build contractor. I don't think it's
necessarily the tools TxDOT has as it is the degree to which
they have embraced partnering with us."
Jeff Overmier, deputy director of construction for LSI with
T.J. Lambrecht, agrees. "It's probably a mindset as much
as anything," he says. "These open forums are real
positive. We resolve issues right away and move forward."
>
Five interchanges with average heights of
60 to 80 ft. Project may eventually
expand
to a six-lane freeway with median to
accommodate light rail system.
> 119 bridges
> Four main toll
plazas
> 29 exit/entrance
ramp toll plazas
> Tolls, approximately
12¢ per mile
> Construction
work force approximately 800;
total work force 1,100 over project's
life. |
That kind of synergy separates not only design-build as a
concept from traditional bidding processes but also demonstrates
the potential success of future private-public partnerships
with TxDOT. "This project will serve as a stepping stone
for future design-build projects in Texas," Daigh says.
"We are certainly not the first to try design-build
in transportation, just the first in Texas," says Weight.
"One of the Texas twists we put in is the concept of
the independent quality [assurance] firms, which is something
that hasn't been done before, to my knowledge, in the nation."
The result is a system of checks and balances. While LSI
assumes responsibility for all quality assurance, from meeting
the design specifications to meeting the completion schedule,
the quality assurance firms are required to remain independent
from any of the developer firms.
"We have two independent firms whose costs are paid
by LSI but report to TxDOT and LSI simultaneously," Weight
says. "That is the first line of inspection forces, if
you will. Over that, we have HDR, our representative, which
also does some checking on the quality firms just to make
sure they're doing things the way they should."
Because much of the project is greenfield, environmental
compliance takes on a much larger role. "We have onsite
environmental compliance inspectors," says John Rempe,
Balfour Beatty's LSI director of construction. "They
are there to make sure we respect all boundaries and to keep
us in compliance through the whole process."
Another key to the success is standardization. "With
standardization you get flexibility, which equals the bottom
line and time," Rempe says. "The merging of the
design-build to the right-of-way, that's really key. The key
element is continuous work."
|