|
Green Thumb
AGC Moves into New Energy-Efficient
Offices:
AGC of America's new headquarters will be housed in the Navy
League Building, the first LEED-certified office building
ever constructed in Arlington, Va.
By Tony Illia
 |
| AGC of America
will occupy 24,000 sq ft inside the Navy League's new
214,000-sq-ft Class A office building in Arlington. |
A sleek new "green" building is helping redevelop
the courthouse district in Arlington, Va., while providing
energy-efficient office space as the new home of the Associated
General Contractors of America.
The seven-story, 214,000-sq-ft Class A office building at
2300 Wilson Blvd. is being developed by the Navy League, a
77,000-member nonprofit group that supports the maritime branches
of the U.S. military.
AGC signed a 10-year lease with two five-year options to
occupy 24,000 sq ft inside the new state-of-the-art building
and provided a $7-million loan toward its construction. The
120-ft-tall building replaces AGC's previous Arlington headquarters
at 333 John Carlyle St., where it occupied 25,000 sq ft for
six years. The construction cost for the new building is $27.6
million.
"The fact that we were able to design our own space
from scratch meant improved efficiencies," says Dave
Lukens, AGC's chief operating officer. "We feel like
this a central location that is much closer to many of the
agencies we work with."
AGC will complete a phased move-in by Oct. 3, occupying most
of the fourth floor with 70 staff members. Its Washington,
D.C., chapter will also share space under a five-year, 1,500-sq-ft
sublease arrangement.
The building contractor was James G. Davis Construction Corp.,
Rockville, Md., with New York City-based Turner Construction
Co. performing AGC's five-month, $900,000 tenant build-out
under a lump-sum contract. Turner's work consisted of placing
drywall, framing, painting, mechanical, electrical, HVAC and
fire systems, says Adriano Nino, Turner's senior project manager.
Designed by WDG Architecture PLLC, Washington D.C., the space
consists of 50 offices, a lunchroom, storage space and three
conference rooms. There also is a dramatic lobby outfitted
with terrazzo flooring, custom millwork and accent lighting.
LEED Accreditation
The new structure is Arlington County's first office building
to achieve a Leadership in Environmental and Energy Design
silver rating. In return for the project achieving the rating,
the county allowed it 12,000 sq ft more space than normally
permitted for the site, giving the owner additional rentable
income.
The county required a $250,000 bond to guarantee the building
achieved the LEED rating from the U.S. Green Building Council.
The county also requested that a consultant oversee the process
and report on the progress being made. MTFA Architecture Inc.,
Arlington, was hired as a LEED submission consultant, along
with CH2M-Hill Cos. Ltd., Denver, Colo., as commissioning
agent. While green construction costs about $1 per sq ft more
than a normal office building, the life-cycle savings from
improved operational efficiencies are expected to recoup the
expense.
|
Founder: President Theodore Roosevelt
Started: 1902
Members: 77,000
Affiliate members: 250 corporate/community
Councils: 330 worldwide
Supports: U.S. Navy, U.S. Marines, U.S. Coast
Guard and U.S. Flag-Merchant Marine Youth Programs,
U.S. Naval Sea Cadet Corps, Navy League Scholarship
Program
Scholarships: $200,000 in annual awards
Staff: 50
Office space: 20,000 sq ft
Operating Budget: $6 million annually
|
The Navy League had owned an aging four-story, 20,000-sq-ft
office building at the Wilson Boulevard address and wanted
to grow. But the 1.3-acre city block had two other property
owners, with a county parking lot on one side and commercial
townhouses holding law offices on the other.
"The land was too valuable not to combine the three
lots," says Bill Keech, president of the Keech Co., Arlington,
which served as the owner's representative. "We realized
the expense in acquiring land could be offset if we could
get additional densities, which factored in our decision to
construct a 'green' building."
The Navy League purchased the county's 19,840-sq-ft lot for
$3 million and agreed to give the attorney 13,000-sq-ft of
rentable office space in exchange for his property. With a
consolidated 49,273-sq-ft site, Davis Construction began work
under a guaranteed maximum price contract.
The parallelogram-shaped block is bordered by Wilson and
Claredon boulevards and North Wayne and North Adams streets
in a commercial/residential area of Arlington. That meant
the contractor faced county-mandated noise restrictions, work
hours and delivery lanes.
"The restrictions meant that we had to stage steel,
concrete and material deliveries using specific lane routing
so as not to disrupt traffic," says David Purdy, Davis
Construction's project manager.
Plans called for a four-level, 358-space cast-in-place underground
parking garage, which meant 60,000 cu yd of excavation and
eight months of dewatering. The contractor also had to remove
5,000 cu yd of petroleum-contaminated soils as well as underground
storage tanks.
Additional shoring and site regrading were needed to accommodate
the Metro's Orange line running under the site. The nearest
station is only a block away.
In order to meet LEED goals, the contractor implemented an
onsite program where 75% of the construction waste was recycled.
This included an awareness campaign with regular subcontractor
meetings and enforcement to ensure materials were being separated
and reused. "There was a significant amount of policing
on the project," says Hasan Alsayegh, Davis Construction's
assistant project manager. "In some instances, we would
have people dive into the dumpster to retrieve an item that
wasn't properly sorted."
Other sustainable components include an underground stormwater
collection system used for flushing toilets and irrigating
trees and shrubs. When combined with the nonpotable-water
toilets and high-efficiency plumbing fixtures, the building's
potable water use is 60% less than a normal building.
HVAC systems and an Energy Star-rated roof helped reduce
energy consumption by 20%. And more than 20% of the project's
materials and subcontractors came from within a 500-mile radius
of the project.
Low-emission adhesives, paints and carpets are used throughout,
and 50% of the wood-based products are certified under Forest
Stewardship Council guidelines to reduce waste.
Design and Structure
|
Lot: 1.3 acres
Height: 120 ft
Stories: 7
Size: 214,000 sq ft
Construction Cost: $27.6 million
Steel: 1,100 tons
Excavation: 60,000 cu yd
Peak work force: 130
Subcontractors: 35
Parking: 358 stalls
Garage: Four levels, underground
Opens: September, 2005
Exterior: Precast concrete panels/glass
Rating: LEED silver
Retail: 30,000 sq ft
Recycled waste: 75%
Tenants: 11-15
Avg. Lease Rates: $35 per sq ft, triple-net
|
Designed by Houston-based architect PageSoutherlandPage LLP,
the steel-framed building rests atop a spread-footing foundation
with concrete-over-metal decking floors. The exterior is clad
with glass and precast panels detailed with gridlines that
both accent and minimize the shape of the building.
"The panels have a pinkish tinge with a subtle color
change from light beige to off-white," says Ben Webne,
PageSoutherlandPage's project designer and construction administrator.
"The floor plates are offset to lower the building's
profile while creating balconies at each level."
The building's approval process included community design
charettes, which contributed to its stepped profile so as
not to obstruct neighbors' views. It also added amenities
such as 30,000 sq ft of ground-level retail space, a fitness
center, landscaped plaza and 3,000-sq-ft community conference
facility.
The two-story lobby features a grand staircase and a dramatic
glass wall by Vancouver-based Joel Berman Glass Studios Ltd.
The 1,200-lb architectural glass wall consists of six 9-ft-tall
by 4.5-ft-wide cast panels that were assembled onsite.
The building will house 11 to 15 tenants, with office lease
rates averaging $35 per sq ft, triple-net. Lincoln Property
Co., Dallas, is the property manager; Houston-based Transwestern
Commercial Services is the office leasing agent; and Asadoorian
Retail Solutions, Washington, D.C., is responsible for the
retail areas.
The Navy League's 50-person staff will occupy 20,000 sq ft
on the second floor of the unique structure. "We wanted
a building that would satisfy our needs for additional space
while better serving our constituency," says Howard Siegel,
the Navy League's senior finance director. "This is going
to be our home for the next 100 years, so we wanted to set
a high standard by constructing the county's first silver
LEED-certified building."
|