AGC of America Member Login AGC of America HomeAGC of America About AGCAGC of America Contact UsAGC of America Find a ContractorAGC of America Find a ChapterAGC of America
Print this Page Sitemap Email to a Friend
MARCH/APRIL 2006:

Cover Story:
2006 AGC President

Features: 
What We Build:
Opera House Renovation
Earthquake Proof
Maine Bridge 
Features: 
Issues & Trends:
Immigrant Workers
Mold Issues Update 

Departments:
Editor's Notebook
Guest Commentary
Legal Commentary
The Punchlist
Info Tech:
Work Track
Graphisoft
MobileDataforce

Inside AGC:
President's Message
CEO's Message
Chapter Corner
Financial Advocacy
Advocacy Update
Meet Your Leaders
Industry Issues

 

View all archives >>
<< Home

 

Features: What We Build — March/April 2006

Maine DOT Finds Success With Portland Connector

A $25-million bridge connector project cements state's use of design-build for highway projects

By Sheila Bacon

The $25-million Portland Connector project links the Outer Congress Street exit of Interstate 295 with West Commercial Street and Portland, Maine's working waterfront. The project was completed using design-build, shaving nearly two years off the project schedule.
Photo by Mark Shain

Completion of a complex road- way construction project in Portland, Maine, has eased congestion, improved waterfront access and proven the effectiveness of the design-build process on highway jobs.

The Maine Dept. of Transportation's use of design-build on construction of the $25-million Portland Connector-which links the Outer Congress Street exit of Interstate 295 with West Commercial Street and Portland's working waterfront-enabled the project team to bring the roadway to completion nearly two years earlier than what would have been expected under traditional design-bid-build.

The scope of work included construction of nearly 1 mile of new roadway, three new bridges and the replacement of a traffic rotary with an at-grade intersection. The job also included more than a mile of pedestrian and bicycle trails, furthering the vision of a long-anticipated Fore River Trail that will connect the Fore and Stroudwater River trails to Portland's Old Port.

The key to the project's success was the ability to start construction on portions of the project well before design was finished elsewhere, which would have been impossible under traditional procurement methods that put a project out to bid only when the entire design was complete, says Shawn Smith, project manager with the Maine DOT.

Here, contractors got moving early on an 18-month preload of the road bed, which consolidated the site's marine clay in preparation for construction. While the site was compressing, designs were finalized on other portions of the project and work was able to start on the new intersection.

Designers and contractors also were able to craft a complex traffic management plan, one that involved detailed input and expertise from more than 40 stakeholders.

The building team sets steel on Bridge 3, one of three bridges along the Fore River.
Photo courtesy of Maine DOT

With all team players working together in the design-build environment, efficiencies not typically associated with publicly bid work were realized.

"We were all pushing on each other to get answers," says Mark Barnes, project manager with Associated Constructors of Maine member firm Shaw Bros. Construction, of Gorham, the job's earthwork subcontractor. "We were able to manage things much faster and get things accomplished much quicker."

Past Success

Maine DOT became familiar with the design-build method in 2000 with the construction of the Sagadahoc Bridge between Woolwich and Bath. Its smooth completion and substantial time savings made the project a success, so when the Maine legislature later approved design-build for highway construction, the DOT began its search for a team that could handle the Portland Connector job.

"Bridges are complex," Smith says. "[The Sagadahoc Bridge project] proved that the design-build method can be useful and showed us what a team can come together and do."

The DOT advertised the highway job in August 2002 and in less than a year had found its team: general contractor Cianbro Corp., Pittsfield, Maine; earthwork contractor Shaw Bros. Construction; the Manchester, N.H., office of engineering firm Louis Berger Group; and geotechnical engineer S.W. Cole Engineering, Gray, Maine. Work began two months later.

"All the candidates' proposals indicated multiple tasks going on all the time, but the Cianbro team had a better consistency to it," Smith says. "Right off the bat, they got the geotechnical program working."

Extensive Prep Work

The area's clay-rich soil required considerable attention before work could begin. Crews preloaded portions of the roadway, adding fill atop the spongy soil. The nearly year-and-a-half-long exercise squeezed excess water from the soil and compressed the ground to minimize future settling.

Crews start construction of a retaining wall as part of the Portland Connector project.
Photo courtesy of Maine DOT

While the future roadway site was compressing, design continued elsewhere on the project. Crews performed utility relocations and focused on Veteran's Circle-one of the busiest traffic rotaries in Maine. A multi-stage plan to demolish the rotary, remove two flyover bridges and construct a new intersection was put in place-all while maintaining the flow of more than 20,000 cars through the area each day.

Construction of the project's three bridges followed, finishing with the roadway connecting the entire project.
A detailed plan to alleviate congestion at the busy Veteran's Circle was the focus of a half-day planning session held before work started. Representatives from the city, state, design and construction team, and surrounding businesses and neighbors came together to talk about specific needs and potential impacts.
Business owners detailed where and when their deliveries might be affected by construction, and municipalities shared rush-hour traffic patterns with the group. This pre-planning discussion helped form the eventual phasing of work and resulted in a process that kept traffic moving throughout construction.

"That's one of the things the DOT can't do in the design phase [under a typical design-bid-build scenario] because we don't know how the contractor is going to attack a project," Smith says. "In this case, because we have the contractor right there, we can work some of these things through immediately, months before construction has even started."

"What could have been a massive hemorrhage of traffic problems turned out to be a smooth-flowing plan," says Lou Campbell, project manager with Associated Constructors of Maine member firm Cianbro Corp.
Before road construction started, Shaw Bros. used a satellite global positioning system to perform the majority of the layout and grading of the site, cutting surveying time by at least 50% and greatly reducing the possibility of human error, says John Allen, the firm's grade layout foreman.

Surveyors used Real Time Kinematic GPS to take measurements, a system relatively new to highway construction applications, which provided a 95% confidence level within an inch on horizontal measurements, Allen adds. Maine DOT was so impressed that it asked Allen to make a presentation detailing Shaw Bros.' use of the system on construction projects to its surveyors at a DOT conference.

The use of GPS allows one person to map the site remotely instead of sending two people into the field with stakes and survey equipment.

An aerial view of the Portland Connector project shows the completed job from west to east.
Photo by Don Johnson Photography

"It's a complete 180° change from how things have been done on DOT projects," Allen says.

Substantial Savings

The general contractor's early involvement in the conceptualization and design of the Portland Connector helped economize several aspects of the project, Campbell says.

For example, the ability to offer value-engineering input resulted in a completely different approach to construction of the Danforth Street portion of the job than crews had initially anticipated. Crews expected to remove all the asphalt, curbing and other components of the existing road before building the new section. However, it was discovered early on that the existing roadway was fairly new, enabling the contractor to reuse curbing and scale back planned excavation and paving work.

"It represented quite a savings for the people of Maine," Campbell says.

In-person collaboration with the stakeholders, neighbors, owner and builders was vital, says Dale Spaulding, design project manager and Berger vice president. The design-build process made that interaction possible, something that wouldn't have happened in a conventional design-bid-build situation.

"Typically, as designers, we work with design reviewers at the state agency who never have input from the contractor," Spaulding adds. "Eighty percent of the time the contractor comes on board and wants to do things a different way. Here, we all came up with a plan that was real instead of working in a box with a bunch of traffic engineers saying, 'This is the way it should go.'"

Relationships formed among the design-build team and dozens of business owners and neighborhood groups during preliminary studies were strengthened through formal gatherings as well as informal partnering sessions. The outreach proved to be more than a good will gesture.

Discussions at one of the meetings resulted in a complete redesign of truck storage lanes near the Cassidy Point business district to accommodate the needs of the area's business owners while creating a more efficient traffic scheme.

"The term 'teamwork' can sometimes sound like a cliché, but the meaning is true when it's applied wholeheartedly," Spaulding says.

The Portland Connector opened to traffic on Nov. 18, 2005.

 

 

Constructor is a publication of McGraw-Hill Construction [ © 2007, all rights reserved ]
Terms of Use | Privacy Policy | Contact Us