|
|
Damage Control
Replacement of Florida's Escambia
Bay bridges on a fast track
By Bruce Buckley
 |
Crews are pushing hard
to replace the first of two Interstate 10 bridges over
Escambia Bay near Pensacola, Fla., before a Dec. 29 contract
milestone.
Credit: photo courtesy of skanska |
Crews replacing the Interstate 10 bridges over Escambia Bay
in Florida's panhandle are hoping for a happy holiday season.
The design-build team, led by Tidewater Skanska, Virginia
Beach, Va., and Flatiron Constructors, Longmont, Colo., is
aiming for a Dec. 29 contract deadline to complete the first
of two 2.6-mile-long bridges opening, two lanes of traffic
in each direction across the bay.
The Escambia Bay bridges, east of Pensacola, were severely
damaged by Hurricane Ivan in September 2004 when storm surge
displaced several sections of decks into the bay. The Florida
Dept. of Transportation then put out a request for design-build
proposals in its effort to quickly restore traffic flow through
one of the state's major arteries.
To help drive the urgent message home with construction firms,
FDOT offered to award a lump-sum $10 million bonus for completing
the eastbound span by Dec. 29, 2006. If the team misses the
deadline, it will pay a penalty of $133,000 per day. The entire
$243 million project is scheduled for completion in November
2007.
Soon after the storm, the state determined the bridge should
be replaced rather than rehabilitated and that an incentive-driven,
design-build contract would be best, says Steve Hunt, operations
engineer with FDOT in Milton, Fla. It was in the best interest
of taxpayers to open it as quickly as possible, he says. "Hang
a $10 million carrot out there, and you get a lot of attention."
 |
|
At any one time, the Escambia Bay
bridge site is home to as many as 21 large-capacity
cranes lifting pieces into place.
Credit: photo courtesy of Parsons Brinckerhoff Quade
& Douglas, Inc.
|
While plans for the new bridges were in the works, the state
entered into an emergency contract with Gilbert Southern,
Lakeland, Fla., an affiliate of Kiewit Corp., Omaha, Neb.,
to restore traffic across the existing bridges.
Undamaged spans from the eastbound bridge were removed and
used to replace gaps in the westbound bridge, creating two
lanes of traffic. A temporary steel-panel bridge system, supplied
by Acrow Corp., Carlstadt, N.J., was placed in the eastbound
gaps to carry 42,000 vehicles a day. The work was completed
in 17 days.
While the quick fix got traffic moving, the deal with Tidewater
Skanska and Flatiron aimed to provide new bridges that meet
future hurricane requirements and traffic demands. Parsons
Brinckerhoff Quade & Douglas, New York City, designed
the two new bridges being built south of the existing bridges.
They will have 10-ft shoulders and can accommodate three lanes
of traffic, while the existing bridges have only two lanes
with narrow shoulders.
To help the bridges weather future storm surge, the spans
are being built no less than 25 ft above mean high-tide levels-more
than twice the height of the existing bridges. Over the navigation
channel, the spans will reach 65 ft above the water-10 ft
higher than the existing bridges. The spans were also designed
to meet current ship- impact requirements.
Picking Piles
 |
|
To help the bridges weather storm
surge, the new spans are no less than 25 ft above mean
high-tide levels. At the navigation channel, the spans
are 65 ft above the water.
Credit: photo courtesy of Parsons Brinckerhoff Quade
& Douglas, Inc.
|
PBQ&D designers had to scramble to create a new vision
for the I-10 bridges, says John Poulson, design project manager
at the firm. "We only had about three weeks to put the
proposal together," he says. "In that time, we took
the whole bridge to 30% design, with certain elements at 60
to 90%. It had to be at a level the joint venture was comfortable
with."
Among the design highlights are the 36-in.-square precast
piles, the first time piles that large have been driven on
a FDOT project. The larger piles created several advantages,
Poulson says. With wider piles, crews would have to drive
only five piles for each substructure unit. Standard 30-in.
piles would have required seven or more per unit. "Otherwise,
we would've needed a pier structure that required more cast-in-place
concrete," Poulson says. "There was efficiency in
the total number of pieces that went into making a given span."
The piles, precast beams and caps each weigh roughly the same.
"There was some balance, so once you get your equipment
out there, you can pick everything up with the same equipment,"
he adds.
 |
|
Crews have battled geotechnical
issues, with highly variable soil conditions recorded
from pile to pile as they were driven.
Credit: bottom photo courtesy of Parsons Brinckerhoff
Quade & Douglas, Inc
|
While the team had a solid design to work from, geotechnical
issues at the site were less certain, says Bryan Estock, senior
project engineer with Parsons Brinckerhoff Construction Services,
Tampa, part of the construction engineering and inspection
team. As the first test piles were driven in July 2005, engineers
noticed highly variable soil conditions. "It wasn't just
varying from bridge to bridge or span to span," Estock
says. "It was from pile to pile." As a result, longer
piles were used. Most are 145 ft long, with the longest measuring
170 ft and weighing 80 tons.
The team has used a mix of barges and templates mounted on
the bottom of the bay to drive the piles. Maneuverability
in the shallows of the bay has been difficult, says Jay Erwin,
project manager with Tidewater Skanska/ Flatiron Constructors.
Nearly 15% of the bridge crosses water between 2 and 3 ft
deep. To save time, crews first drove piles in the deepest
areas while platforms were built in the shallows.
Coordinating equipment movement also has been tricky. At
any one time, the site has 21 large-capacity cranes, two Raymond
60X air/steam hammers, two Conmaco air/steam hammers, a large
fleet of barges and other floating equipment.
|
John Poulson, Design Project Manager,
Parsons Brinckerhoff Quade & Douglas
|
Hurricane Katrina in August 2005 did little damage at the
site, but it disrupted the flow of materials. Precast concrete
elements were coming from two yards-Standard Concrete Products
in Tampa and Gulf Coast Prestress in Pass Christian, Miss.
Standard was not severely impacted, but Gulf Coast was wiped
out.
While the team looked for new suppliers, FDOT agreed to modify
the design to meet the Dec. 29 deadline. "Under the original
design, we would divert two lanes of eastbound traffic onto
the new bridge and demolish the existing eastbound sections
to complete the tie-in," Estock says. "With the
modification, we widened eastbound farther south to carry
four traffic lanes, without demolishing the existing eastbound
bridge." When the new bridge is completed, crews will
finish the westbound span and roadway approaches in time for
the November 2007 opening.
PROJECT DETAILS
24-in. concrete piles: 5
36-in. concrete piles: 1,274
Precast pile caps: 133
Cast-in-place pile caps: 934 cu yd
78-in. Bulb-T girders: 986
Post-tensioned girders: 30
Type II girders: 63
Concrete placed for 71,881 cu yd
substructure and superstructure
Steel reinforcement: 20,263,683 lbs
Fill: 39,476 cu yd
Asphalt: 10,263 tons |
KEY PLAYERS
Owner: Florida DOT, Milton, Fla.
Design-Build Team:
Designer: Parsons Brinckerhoff Quade & Douglas,
New York, N.Y.
Contractors: Tidewater Skanska, Virginia Beach,
Va.; Flatiron Constructors,
Longmont, Colo.
Geotechnical: Ardaman & Associates, GRL Engineers,
both Orlando, Fla.
Post-Tensioning: VSL, Fort Lauderdale, Fla.
Earthwork: Delta Contractors, Pensacola, Fla.
Paving: Anderson Columbia, Lake City, Fla.
Steel/Rebar: D.T. Read, Pensacola, Fla.
Concrete: Ready Mix USA, Pensacola, Fla.
Construction Engineering and Inspection Team:
Prime CEI: Parsons Brinckerhoff Construction
Services, Tampa, Fla.
Inspection: PBS&J, Orlando, Fla.; Mehta &
Associates, Winter Park, Fla.
Geotechnical: PSI; Foundations & Geotechnical
Engineering, both Tampa, Fla.
Acrow Bridge Inspection: Kissinger Campo &
Associates, Tampa, Fla.
|
|